Understanding the Demised Envelope & Dual Consent
In a London leasehold flat, your ownership is limited to the demised envelope (the internal envelope), which will normally be the plaster, the non-structural stud walls, the kitchen cupboards, the sanitaryware and the branch pipework, which serves only your flat. The structural concrete slabs, the external cladding, the windows and the communal service risers are all counted as the freeholder’s property.
Because your apartment sits inside an interconnected structure, high-rise refurbishments are governed by a strict two-tier gatekeeper system:
- Contractual leasehold consent: prior to any alteration to layout, flooring, or mechanical services, you will require a formal Licence to Alter from your freeholder or Principal Accountable Person. That will ensure that any works don’t breach the noise covenants or in any way compromise the Fire Safety Case.
- Statutory BSR Approval: For residential towers of 18m, or 7 storeys and above, any non-exempt work, which has an impact on the structure, fire compartmentation, or shared services, requires prior Building Safety Regulator (BSR) building control approval. That is a hard stop under the Building Safety Act; you can’t start on site without that approval.
Before you go and instruct the architects or contractors, you need to get your lease terms reviewed by Crown Luxury Homes’ City Management & Advisory Division to ensure that you are operating within the rules, and that the scope of works is one which is value accretive.
What You Generally Can Do (Permitted & Exempt Works)
A number of interior upgrades in London high rise apartments are outside the scope of the BSR application, as long as the building’s structure, fire strategy and shared services are not altered:
- Cosmetic and decorative works: (painting, wallpapering, soft furnishings, non-structural fitted joinery, etc.) generally won’t require a Licence to Alter or BSR consent. That said, the managing agents will still need to be notified in advance of any service lift bookings and any common part protection.
- Like-for-like kitchen and bathroom replacements: (i.e. replacing the cabinetry, worktops and sanitaryware within the existing footprint using the existing pipework) are generally allowed. Where the fire compartmentation is not affected, the electrical and heating works will be subject to self-certification under a registered Competent Person scheme (NICEIC or Gas Safe etc.), rather than full BSR approval.
- Smart controls and lighting: smart thermostats, automated blinds and upgraded lighting can be installed where certified under Part P and specified, provided that the recessed fixings do not in any way compromise the fire-rated or acoustic ceiling voids.
- Non-structural layout changes (with prior consent): removal or repositioning of non-loadbearing stud partitions is possible on obtaining a Licence to Alter, and with prior BSR approval that the protected escape routes are still compliant.
Consult the City Management & Advisory Division of Crown Luxury Homes prior to instructing contractors to check which works are exempt and to ensure that the works are delivered in a compliant and value accretive manner.
What You Strictly Cannot Do (Prohibited & Restricted Works)
As the high-rise flats are situated within a common structure, there are a number of standard types of refurbishment, which are either expressly prohibited or heavily restricted under the lease covenants and the BSR rules:
- Alter structural elements: cutting chases into, or removing load-bearing columns, shear walls or concrete slabs is absolutely prohibited.
- Modify facades, windows or balconies: replacing window frames, drilling vents through the cladding, enclosing winter gardens, or placing air conditioning condenser units on the balcony all breach the regulated fire and thermal envelope.
- Compromise Fire Compartmentation or Entrance Doors: The apartments are effectively sealed fire boxes. Running unsealed cables through party walls, or in any way modifying a certified flat entrance fire door (FD30S/FD60S), including unauthorised lock changes, will invalidate the Fire Safety Case.
- Lay hard flooring without acoustic sign-off: the majority of City leases will require carpets or a certified acoustic underlay meeting strict impact sound criteria. Hard flooring (timber or stone) laid without such approval will normally result in a breach of lease notice, and the floor will have to be removed.
- Relocate wet zones over dry rooms: moving a kitchen or bathroom above a neighbour’s bedroom or living area is pretty much always refused on the grounds of noise, and risk of water escaping.
- Tamper with communal plant and risers: any modification to the Heat Interface Units (HIUs), Fan Coil Units (FCUs), sprinklers or soil stacks without engineering approval will have a detrimental effect on the building’s systems as a whole.
Consult the City Management & Advisory Division of Crown Luxury Homes prior to commissioning any designs to confirm that the proposed works are compliant and value accretive.
Timelines, Costs and Conveyancing Fallout
Refurbishing an apartment in a London Higher Risk Building requires proper scheduling and an upfront compliance budget before any contractor actually gets on site:
- The ‘Hard Stop’ Approval Rule: under the Building Safety Act, it is a statutory offence to start notifiable work prior to receiving formal Building Safety Regulator (BSR) building control approval. In the case of BSR refurbishment assessments, this is a very strict legal gate, and they routinely require several months’ lead time, as well as concurrent freeholder review.
- Budgeting for dual consent: the owners will need to factor in the compliance fees as part of their pre-construction budget. A formal Licence to Alter will involve payment of the freeholder’s surveyor review fees, the landlord’s legal drafting fees, and your own solicitor’s fees, as well as the statutory BSR application and inspection fees.
- Protecting the resale and refinancing value of the property: unauthorised alterations create massive conveyancing bottlenecks. Missing Licences to Alter, missing BSR completion certificates, or unrecorded changes to the Golden Thread surface of the building will all come to light during the buyer’s solicitors’ enquiries, and will either stall the exchange, disrupt the remortgage, or necessitate the very expensive retrospective regularisation and the associated indemnity.
Before you go and engage any architects or contractors, you must first consult with Crown Luxury Homes’ City Management & Advisory Division to get the approvals in the right order, and to safeguard the long-term liquidity and value of your property.
Why Crown Luxury Homes?
You need local expertise on leasehold covenants and BSR rules before you commit any capital. Crown Luxury Homes’ City Management & Advisory Division provides specialist support to Square Mile apartment owners, buyers and portfolio landlords in three key areas:
- Pre-reno value advisory: before you even get the architects or the contractors on board, we will assess your proposed specification against current buyer and corporate tenant demand to establish which upgrades are actually commanding a premium in rental and/or resale, and which are just adding compliance cost with no real return.
- Managing Agent and Concierge coordination: our City property management team are working on a daily basis with the managing agents and Principal Accountable Persons across the leading Square Mile and City Fringe residential towers. We are very much involved in the coordination of contractor protocols, the service lift logistics, and the formal Licence to Alter submissions from the very beginning.
- Transaction-ready documentation: we will get every alteration licence, every competent person certificate and every BSR completion record properly compiled and logged into the building’s Golden Thread to protect any future lettings, sales or refinancing from being held up by a lack of documentation.
Before commissioning architects or contractors for your high-rise refurbishment, consult Crown Luxury Homes’ City Management & Advisory Division to ensure your planned upgrades are fully compliant and value-accretive.
High-Rise Renovation Compliance Matrix
| Scope of Work | Freeholder / Managing Agent Rule | Building Safety Regulator (BSR) Rule (18m+ Towers) |
| Painting, Decorating & Loose Joinery | Courtesy notice for contractor access and lift protection. | Exempt (minor work not affecting structure or fabric). |
| Like-for-Like Kitchen / Bathroom | Written notice; adherence to building contractor rules. | Exempt if footprint and fire barriers are untouched; requires Competent Person sign-off. |
| Hard Flooring Installation | Formal written consent + acoustic underlay verification. | Must comply with Building Regulations Part E acoustic standards. |
| Moving Stud Walls / Layout Changes | Formal Licence to Alter (surveyor & legal review). | Mandatory prior BSR approval required before work starts. |
| Relocating Kitchens, Bathrooms, or HIUs | Formal Licence to Alter (frequently refused over dry rooms). | Mandatory prior BSR approval required before work starts. |
| Facade, Window, or Structural Changes | Strictly prohibited (outside demised premises). | Prohibited without freeholder & formal BSR gateway approval. |